Which of the following is an example of supplier preassembly that can reduce field labor costs on an electrical job?
0
1
Tags
Electrical Contracting Business Operations
Running an Electrical Contracting Business Course
Related
When an electrical contractor utilizes supplier preassembly, such as ordering fixtures that are already pre-whipped and pre-lamped, the estimator should expect a reduction in both material costs and field labor costs.
As an estimator or project manager reviewing site inefficiencies, match each labor-wasting field scenario with the specific supplier preassembly or packaging choice that would best resolve it based on the concept of labor-reduction.
An estimator is evaluating supplier preassembly for a commercial lighting project. Standard boxed fixtures cost $8,000 in materials and require 100 hours of field labor to assemble and install. Pre-whipped and palletized fixtures cost $9,500 in materials but reduce the field labor to 60 hours. If the company's burdened labor rate is $50 per hour, choosing the pre-assembled option will result in a net overall cost savings of ____ dollars.
You are an estimator preparing a bid for a large commercial lighting project with 500 fixtures. You want to determine whether ordering pre-assembled options (such as fixtures that arrive with wiring connections and lamps already installed, or fixtures shipped on pallets instead of in individual boxes) will produce a net cost savings compared to buying standard unassembled materials. Arrange the following decision steps in the most logical and effective order for making this evaluation.
As the owner of a new electrical firm, you are designing a 'Standard Procurement Specification' to ensure your team spends as little time as possible on non-installation tasks. Which set of requirements should you create for your lighting suppliers to best utilize the principle of supplier preassembly for a large-scale commercial project?
You are developing a 'Labor-Optimization Procurement Plan' for your electrical company's upcoming commercial contracts. To create a purchasing specification that maximizes the benefits of supplier preassembly and reduces site overhead based on the strategies discussed, which integrated package should you design?
Your electrical firm is working on a high-rise office renovation where the building manager has banned the storage of cardboard on-site and the freight elevator is only available for a very short window each morning. Which application of 'Supplier Preassembly' would be most effective in overcoming these specific logistical challenges?
You are an estimator for an electrical firm bidding on a project that requires 100 light fixtures. You can buy standard fixtures for $50 each, or 'pre-lamped' fixtures (with bulbs already installed) for $56 each. You estimate that it takes your crew 10 minutes to unbox and install a lamp in each fixture in the field. If your total labor cost is $48 per hour, how should you apply the principle of supplier preassembly to your bid?
Based on the economic trade-off discussed in the video, why would an electrical contractor choose to pay a premium (a higher unit price) for 'pre-whipped' and 'pre-lamped' fixtures?